22 October 2008

The lids off the paint...

The main effort over the last couple of weeks has been the settee berths. We have made these wide enough to be comfortable bunks, about 700mm. This is 80-100mm wider than the old starboard settee berth and the few times I have tested them out, they seem excellent.

Up forrard I have been Interprotecting all surfaces prior to finishing with Perfection Undercoat. It is really stinky stuff and a good vapour mask is essential. If you don't have a fan going your eyes start watering! It is starting to feel more like a boat again, in parts, rather than a demolition site.

On deck, we have glued the fiberglass flat bar into the routed part of the bulwarks and I have been sealing holes by the dozen. Next on the program is adding a layer of filler on the top edge, sand it flat, rout a radius on the corners and fiberglass tape over it all. Can't say I am looking forward to the longboard!

06 October 2008

Watertanks and chainplates

So, the last few weeks have seen the watertanks finally completed, new chainplate members glassed in and the torture of the gunwhale routing finished.




The tanks took a little longer than I had thought, but I believe the results are worth it. My measurements show we should get about 270 litres per side (I think that means about 120 Imperial gallons total, or 135 of those funny US gallons). Breathers will exit up the mast, which should work nicely. There will be another, smaller tank installed to take watermaker production, which in turn will cascade down to the main tanks when full.






The forward and cap chainplates will connect to laminated plywood which has been bonded to the hull, reaching down to the top of the tank and more or less lining up with the tank baffles. This area of the boat should be a lot more rigid than the original, especially with the new bulkheads which are close to the cap chainplates.







The forward cabin has had sealed plywood glued to both the deck and to the sides of the coachroof. We used bendy ply, especially useful for the coachroof sides where we needed to fair the roof into the sides. This has given us a surface that is able to be painted, it won't be completely fair but it will look OK we think. Time will tell.

The forward end of the coachroof was the most difficult and we had to put a few judicious slits in the ply to accommodate the multiple curves. It will require a bit more fairing but should be the worst part of the job, everything else "should" be easier.

The bulwarks under where the genoa tracks will be have been routed out and the fiberglass bar has arrived. Routing out a 20 x 25mm slot 3.5 m long was not pleasant and I blew up one Ryobi router. Still, with the price difference between that and a new Makita, I will be able to blow up another 4.5 Ryobi routers and still be ahead. We are ready to epoxy the bars in place, with LOTS of spare glue to force down the large voids in the bulwarks, where the hull and deck were supposed to be joined (but weren't).

Pretty close to epoxying up the fairlead areas, after I removed the damp and/or rotting wood. I need to look at the original method of securing the fairleads in place as it is not particularly effective. Many of the screws holding the fairleads in did not actually land in anything, which has led to water getting in.

09 September 2008

Spring is coming

With the expected delivery trip from Brisbane to the Seychelles now not happening (a long story), it is now a little easier to get stuck into the job. Main construction work in the forepeak is now finished - finishing and lining yet to do - and our attention is now focused in the saloon area. The next step is constuction of the water tanks, which will be glassd into the hull beneath the floor. We have already covered the top of the keel and the relevant bilge area with several layers of chopped strand mat and vinylester in preparation for this and here you can see Bill has cut out the ply in readiness for glassing in. Yes we have remembered to cut holes out of the baffles!

This shot shows the starboard shelf above the v-berth. It serves to strengthen the panel (quite a large flat surface) as well as provide a little storage.

We have also been busy cutting out holes for the additional deck hatches and portlights. There are two small hatches on top, above the galley and the relocated head, and a portlight on each side of the companionway.

Portlight surrounds are nearly complete, the next step will be to cut the flange down to size and then they will be ready to attach. I have a portlight sitting in place so we can work out how much flange to remove.

22 August 2008

While the cats away...

Very happy to return after a month spent delivering a 109' sportsfishing boat (not my idea of a boat in the slightest), to find progress aplenty. The forecabin has taken shape and we have prepared for the next major bulkhead to be installed, which will be the forward end of the head (starboard) and the forward end of the galley (port).

At the aft end of the bunk there are open-fronted lockers on both sides.

The v-berth has been raised about 80mm from the old level, which should increase it's size as well as improve the stowage beneath. All bulkheads and significant furniture is glassed to the hull, deck and cabintop where posible, so the boat should be a lot stiffer and quieter that the old soggy egg carton.

After stripping off the old glass layer from the top of the keel and allowing it to dry out, we have relaid several layers of chopped strand mat.

This has given a nice smooth area on top of the keel and up the bilges, where the 2 main water tanks will be built in. We used vinylester resin for this as it is the best tank coating.